We have been advised by Bruce Michael, the Garrett County Lake and Watershed Coordinator that Byco Enterprises(the contractor for the Arrowhead dredging project)  has confirmed that the Arrowhead Cove docks can stay in the water through October 15th and hopefully be removed early the week of October 16th. This will allow docks to remain in the water through Autumn Glory. The County is waiting for a more specific date for when Byco will begin in-water construction.

Negotiations with Brookfield to lower the water levels towards the lower end of the rule band beginning in the middle of October continue.  